Project Details
Project Overview
Project Area Map
LACMTA proposes to construct the East San Fernando Valley Transit Corridor Phase 1 Project, a 6.7-mile at-grade light rail transit (LRT) system with 11 stations, nine traction power substations, overhead contact system, and a maintenance and storage facility.
The Project would improve mobility in the area by:
introducing an improved north-south transit connection between key transit hubs/routes;
enhancing transit accessibility/connectivity for residents to local and regional destinations and activity centers;
increasing transit service efficiency; and
encouraging a modal shift from driving to achieve reductions in greenhouse gas emissions.
This transit project - forecasted to open in 2028 - will use the same rail technology as Metro’s A, C, E and L Lines adding 14 new stations between the G Line (Orange) Van Nuys Station and the Sylmar/San Fernando Metrolink Station. This system for the Valley means better transit with improved quality and service.
LACTMA Project Homepage:
https://www.metro.net/projects/east-sfv/
Phased Approach
Phase 1: Preconstruction Services
Phase 1 Work consists of preconstruction services during which the Contractor shall work collaboratively with LACTMA to:
TASK 1 - Project Administration
TASK 2 - Validation of Base Design
TASK 3 - Iterative Value Engineering
TASK 4 - Update Base Design Opinion of Probable Cost
TASK 5 - Develop Design Management Plan
TASK 6 - Permits, License, and Agreements Management
TASK 7 - Cost Estimates and Phase 2 Proposal
Start: Late 2022
DBE Goal: 19.33%
Estimated Phase 1 Cost: $30 mill. to $50 mill.
Phase 2: Design and Construction
The Phase 2 Work consists of services during which the Contractor shall work collaboratively with LACTMA to:
TASK 1 - Identified Early Work Packages
Long Lead Item Procurement
Utility Adjustments
Design to Approved for Construction and Design Support During Construction
Geotechnical
Investigative Works
Hazardous Materials
Cable Transmission System (CTS)
Demolition
Integrated Project Management Office
Task 2 - Complete All Construction Work
December 2023 – December 2027
DBE Goal: Expected
Estimated Phase 2 Cost: TBD
Potential scopes: COMING SOON